Our team on the Cairns Water Security Stage 1 (CWSS1) project has reached a major construction milestone, with several key infrastructure elements now complete as the project moves into pre-commissioning and testing.
Over the past two years, the team has installed 30 kilometres of new pipeline, built a new ultraviolet (UV) treatment building and delivered the project’s 5 megalitre (ML) and 8ML storage reservoirs.
The three-storey administration building is also nearing completion, while pre-commissioning activities, including connecting electricity, are now underway to prepare the infrastructure for testing.
As the largest infrastructure project in Cairns’ history, CWSS1 will help secure the city's future water supply and support a growing population for years to come.
The project includes a new water intake at the Mulgrave River, a new water treatment plant and reservoirs at Gordonvale, as well as supporting infrastructure to connect the new intake to the existing network. It also includes flood resilience upgrades at Council's Behana Creek intake to improve the reliability of the region's water supply.
We’re proud to deliver this nationally significant project for the @cairnscouncil, funded by the Australian and Queensland governments through the National Water Grid.