With a clearance of 5.4m under the rail bridge, the new underpass will help move trucks and heavy vehicles off local streets and out of Dandenong's CBD.
Behind the new underpass was a technically complex program of works, which included relocating one of Melbourne's largest gas supply pipelines and excavating 13 Olympic swimming pools worth of soil to build the new connection.

The team also built a new walking and cycling path along Webster Street that connects to the existing Dandenong Trail and provides safer pedestrian and cycling access under the rail line.
Webster St is the 20th level crossing removed by the NWPA team as part of the Victorian Government’s Level Crossing Removal Project since 2017, reflecting nearly a decade of work delivering safer crossings and better connections across Melbourne.